We advised Burgess Biopower on all aspects of financing the redevelopment of a shuttered paper mill into a state-of-the-art 75 MW biomass power plant located in Berlin, New Hampshire, which will burn waste biomass and sell power to the grid. The financing involved several sources of funds, including $63.5 million of new markets tax credit financing with allocation from six CDEs. The project also involved a $90 million section 1603 cash grant in lieu of an investment tax credit or production tax credits. The balance of the project was financed by $200 million of rated bonds provided by a consortium of financial institutions. We also advised with respect to EPC agreement, off-take power purchase agreement with PSNH and all project related agreements.